Beach Hut Rebuild Start Date

click image to enlarge
The Council have contracted Raymond Brown Construction (of Ringwood) to carry out the seafront work and they are due to start early in September 2016 once the schools' summer holidays are over. 

While work is ongoing access to the seafront will be blocked from the path to the west of The White House and the western Hurst Road Car park closed. Pedestrian access to the toilet block will be maintained but both promenades shut from The White House to the slipway by the seafront shelter. 

If the weather permits building work to continue through the autumn and winter the contractors expect to have finished by February 2017.